It is important to understand the different terms and definitions associated with delay analysis and Extension of Time (EOT). Whether you are preparing a contractual letter for An EOT or you need to understand the EOT terms, the following Extension of Time (EOT) Terms and definitions worth reading.
Act of God – a natural occurrence caused directly and exclusively by natural forces without any human intervention, which could not have been reasonably foreseen or prevented by the contractor or any other party to the contract
Adjusted As-Built – a retrospective schedule impact analysis technique that uses a one time, after-the-fact insertion of owner and excusable delays into the as-built schedule to quantify global impact
Adjusted As-Planned – a retrospective schedule impact analysis technique in which delays are incorporated into the original CPM without regard to actual progress or historical work activity data, in order to quantify global impact
As-Built Schedule – an accurate historical representation of the actual sequence of construction and how it was completed
Baseline (As-Planned) Schedule – the target construction schedule based on the contractor’s original understanding of the project and used as the standard by which progress is measured
Cardinal Change – a change (either directed or constructive) to the contract that, because of size or the nature of the changed work, is clearly beyond the general scope of the contract
Change – when a contractor takes on any type of work that deviates from the original contract, or from the scope of work or plan of action reasonably anticipated under the contract
Collapsed As-Built (But-for) – a retrospective schedule impact analysis technique that apportions responsibility for each party by removing all sources of each delay (owner, excusable, contractor) to quantify global impact
Concurrent Delays – independent sources of delay that occur at same time and/or on separate parallel paths of a CPM network
Constructive Change – a change that is not acknowledged by the owner as such when it occurs, but which nonetheless is a change
Contemporaneous Technique – a schedule impact analysis technique applied at the time of the potential schedule impact
Contractor Responsible Delay (CRD) – a delay attributable to the contractor’s actions or inactions
Convenience Termination – contract clause permitting the owner to terminate the contract at the convenience of the owner, based on specific needs of the owner
Default Termination – contract clause permitting the owner to terminate the contract when the contractor is not meeting the contract requirements
Delay – the lack of performance or the extension of time required to complete a project that results from unexpected events; may be caused by the contractor, the owner, third parties, or by unanticipated natural or artificial site conditions
Differing Site Condition – a material, significant difference between the conditions represented in the contract and those encountered on site
Directed Change – a directed written modification to the contract that orders the contractor to make specific changes to the work required by the project plans and specifications
Disruption – the lost productivity that results from interruptions in the planned sequence of operations
Excusable Delay (ED) – as used in the schedule impact analysis techniques, a delay not attributable to either the contractor or owner
Excusable, Compensable Delay – a delay that will serve to justify an extension of contract performance time, as well as award delay damages; a delay at fault of the owner
Excusable, Non-Compensable Delay – a delay not attributable to the contractor or owner, which will serve to justify an extension of contract performance time, but no monetary compensation
Force Majeure – unforeseen events with causes beyond the contractor’s control, for which the contractor is deemed excusable in their failure to perform within the required time limits
Global Impact – a retrospective schedule impact analysis technique that plots all delays on an as-built bar chart, equating the total delay to be the sum total of the durations of all delaying events
Impacted Updated (Veterans Administration) – a schedule impact analysis technique that can be applied in a retrospective or contemporaneous manner, inserting delays into an updated as-planned schedule to quantify impact; separate calculations for each alleged delay-causing event are not required
Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous schedule impact analysis technique in which at the time of modification, the actual status of the job is determined, the schedule is updated, and the delay is inserted to quantify singular impact
Net Impact – a retrospective schedule impact analysis technique that attempts to justify time extension by showing all delaying events on an as-built bar chart, claiming total project delay is the claim for time extension
Non-Excusable, Compensable Delay – a peculiar situation in which an owner and contractor are concurrently delaying the project, and monetary compensation for the owner’s delay can be properly apportioned
Non-Excusable, Non-Compensable Delay – a delay caused by the contractor’s actions and/or inactions that denies the contractor claims for either time extensions or compensation; the contractor may also be held liable for liquidated damages
Owner Responsible Delay (ORD) – a delay attributable to the owner’s actions or inactions
Retrospective Technique – a backward-looking schedule impact analysis technique that is applied upon project completion
Schedule Impact – the potential effect of a delay or change on a project schedule; may be in the form of delay or change in project completion date, delay or change in project sequence, or consumption of float
Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the effect of delay or change on the project schedule
Schedule of Record (SOR) – the current accepted construction schedule, recently updated or revised, to reflect actual progression of the work and resulting changes to the work plan
Suspension – a written directive by the owner to stop all work on the project, either because the contractor has failed to perform in accordance with contract documents, or at the owner’s convenience
Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact analysis technique that recreates the actual status of the job at the time of modification, updates the schedule, inserts delays, and quantifies singular impact; although retrospective in that it is done after the fact, it has a contemporaneous orientation, not a hindsight perspective
Type I Differing Site Condition – a contract misrepresentation; a physical condition encountered on the site that differs materially from that represented in the contract documents
Type II Differing Site Condition – an unknown physical condition encountered that is not represented in the contract, and is not normally expected in the type of construction work performed
Thanks for providing such good content, THis was very helpfull for me as well as i learned something new here. keep sharing such
ReplyDeletestuff with us. if you are looking for eot cranes manufacturer, then
dont hazitate to visit our website, we have collection of grinder eot cranes and hoists etc.
Thanks for sharing about EOT Cranes have a look at Crane Service
ReplyDeleteFarana Crane
Crane Hire
Crane Rental
Thanks for this Extension of time explanation
ReplyDelete