In EPC
project, procurement progress calculation sheet is required to monitor the
procurement status. Once the procurement phase commences, the status is tracked
and monitored closely. Followings are a guide to develop and update procurement
progress data.
Steps to develop Procurement
Progress Data
1) Understand the terms and confirm procurement work steps and weight factors for equipment work category
- Not Yet Start -0%
- Inquiry Issued to Bidders -10%
- Tender Evaluation and Client Approval -5%
- Purchase Order Placement to Vendor -10%
- Received Key Vendor Drawings -5%
- Approved Key Vendor Drawings -5%
- Fabrication (50%)
- Final Inspection Finished -5%
- Ex-Work -5%
- Delivery at Site -5%
Note:
Weight factor (50%) of fabrication work step shall be multiplied with the
actual progress data from vendor’s progress report to determine actual weight
progress.
2) Confirm
procurement work steps and weight factors for material work category
- Not Yet
Start -0%
- Inquiry
Issued to Bidders -10%
- Tender
Evaluation and Client Approval -5%
- Purchase
Order Placement to Vendor -10%
- Fabrication
(60%)
- Final
Inspection Finished -5%
- Ex-Work
-5%
- Delivery
at Site -5%
Note:
Weight factor (60%) of fabrication work step shall be prorated based on the
duration between purchase order issued date and final inspection date.
Procurement work step groupings and weight factor percentage may be different
from your project team’s preferences.
3) Confirm
planned procurement items (if possible, list down the each equipment number)
and Planned Purchase order amount.
Lets' make
an assumption that the following are planned procurement items and planned
purchase order amount.
- Pipe
& fittings –CS [$15,000]
- Pipe
& fittings-SS304 [$25,000]
- Pipe
& fittings-Special items [$10,000]
- Shell
& Tube Heat Exchangers (AHE-105, AHE-106) [$40,000]
- Columns
& Vessel (ACD-140, ACD-145) [$28,000]
- Reactors
(ACR-10, ACR-15) [$18,000]
- Pump
AHP-230 A/B/C [$20,000]
- Pump
ACP-450 A/B [$15,000]
- Compressor
AHC-235 A/B [$ 27,000]
- Compressor
EHC-215 A/B [$ 20,000]
- Control
valves [$12,000]
- Instrument
cables [$35,000]
- Safety
Relief Valve (PRV) [$ 13,000]
- Orifice
Plates and flanges [$7,000]
- Electrical
Cables [$ 35,000]
- Pressure/Temperature
Transmitters [$20,000]
A better forecast
plan can be produced when actual purchase order amounts and the revised
schedules from vendor are available.
4) Secure the
schedule of each procurement work step for each equipment or equipment group
based on that particular requisition number.
5) Calculate
the weighting for each requisition. Example for Pipe & fittings –CS;
weighting = Planned PO amount of pipe & fitting-CS/ Total Project PO amount
which is 15000/340,000 =0.04
Example for Pipe & fittings-CS; Weighted Progress for Inquiry issued to Bidders = Procurement Work Step Weight factors (Materials)*Weighting which is 10% *0.04=0.44%
The total weighted progress should be 100% as work step weigh factor and weighting of each requisition are based on 100% (1). Check the formula again if you couldn't get 100%.
8) Calculate
periodic plan and cumulative plan progress data using Table-1 Schedule data and
Table-2 weighted progress data. For example; periodic progress data for week
ending 10 Oct 2010 =SUMIF('Procurement Progress Sheet'!$F$7:$N$22,'Progress
Curve'!C2,'Procurement Progress Sheet'!$F$27:$N$42)
9) And then, you should get the plan progress data as shown in Table-3.
10) Plot the
periodic and cumulative progress chart as shown in procurement progress chart.
How to update Actual Progress
1) Add the
procurement work step codes for equipment work category in Table-4; E0 - Not
yet Start, E1 - Inquiry Issued to Vendors, E2 - Tender Evaluation and Client
Approval , E3 - Purchase Order Placement to Vendor , E4 - Received Key Vendor
Drawings , E5 - Approved Key Vendor Drawings , E6 - Fabrication, E7 - Final
Inspection Finished , E8 - Ex-Work , E9 - Delivery at Site. Enter the work step
codes for material work category; M0 - Not Yet Start, M1 - Inquiry Issued to
Vendors, M2 - Tender Evaluation and Client Approval , M3 - Purchase Order
Placement to Vendor , M4 - Fabrication, M5 - Final Inspection Finished , M6 -
Ex-Work , M7 - Delivery at Site.
2) Insert the
additional columns such as Work step codes,Cum Weight factor (Work Step),
Weight factor (Fab Step), Overall % Complete, Individual % Complete for actual
progress calculation. See Table-4.
- Work
step codes are entered when the actual work steps are done. Once the work
step code is entered the cum weight factor for work steps is updated
automatically using H LOOK UP function.
- Individual
% Complete is derived from the cum weight factor (work step) +
weight factor (fabrication step) * fabrication progress. The
actual fabrication progress data shall be received from vendor's progress
report.
- Overall
% Complete data is derived from the sum of
each requisition's weightage * individual % complete.
3) Finally,
insert the actual progress data in Table-3 and plot the actual progress chart.
Great blog, impressive and quality work. Thank you so much for your sharing,. it will help a lot to accurate progress monitoring of procurement and presentation.
ReplyDeleteThanks and you are welcome
DeleteImprove your business on social media. Boost your social media management services through www.troopsocial.com.
ReplyDeleteExisting without the answers to the difficulties you’ve sorted out through this guide is a critical case, as well as the kind which could have badly affected my entire career if I had not discovered your website.
ReplyDeleteBest PHP Training Institute in Chennai|PHP Course in chennai
Best .Net Training Institute in Chennai
Powerbi Training in Chennai
R Programming Training in Chennai
Javascript Training in Chennai
I like the trend that content is becoming more and more important.I like the trend that content is becoming more and more important.
ReplyDeleteProcurement Management Software
Purchase Management Software
e Procurement Management Software
Procurement Tracking Software
I truly appreciate this post. I’ve been looking all over for this! Thank goodness I found it on Bing. You have made my day! Thanks again! Keep update more excellent posts..
ReplyDeleteProcurement Management Software
Procurement Management Software India
Procurement Management Software Chennai
e Procurement Management Software
Thank you so much, nice share, hope more people like you, share and share, I hope your knowledge will expand widly
ReplyDeleteI recommend only good and reliable information, so see it: Project Management Services
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteThis article is simply copied from http://www.toolboxforplanning.com/2011/02/developing-and-updating-procurement.html#.YjI213pByUk
ReplyDeleteAs the article is copyrighted, please remove it from the web.
I am glad to be here and read your very interesting article, it was very informative and helpful information for me. keep it up. Chris Redfield Coat
ReplyDeleteI trust you post again soon... Nightwing Jacket
ReplyDelete